What is the optimal solution and maximum net return for the four-project selection example?

The optimal solution selects projects 1, 3, and 4, while excluding project 2. This corresponds to the binary variable values X1=1,X2=0,X3=1,X4=1X_1=1, X_2=0, X_3=1, X_4=1. Under this selection, the maximum net return achieved is 414.

Conditions

  • The model includes four projects with specific returns and monthly costs.
  • The objective is to maximize total net return subject to monthly budget constraints.
  • Variables are binary (Xi∈{0,1}X_i \in \{0, 1\}).

Reasoning, step by step

  1. Solve the integer linear programming model using software.
  2. Identify the values of the decision variables in the optimal solution.
  3. Calculate the total net return by substituting the optimal variable values into the objective function.
  4. Verify that the solution satisfies all budget constraints.

Example

The video states the optimal solution is X1=1,X2=0,X3=1,X4=1X_1=1, X_2=0, X_3=1, X_4=1. The calculated optimal return is 414. Checking the January constraint: 58(1)+44(0)+26(1)+23(1)=58+26+23=107≤12058(1) + 44(0) + 26(1) + 23(1) = 58 + 26 + 23 = 107 \le 120, which is feasible.

Common misconceptions

  • Assuming all projects with positive returns should be selected.
  • Believing the optimal return is the sum of all individual project returns without considering budget limits.
  • Confusing the cost coefficients with the return coefficients when calculating the final value.